Junction function
Fixing CH ceiling panels to the supporting beam = the same thermal-break system as in freezer walls (p. 23). Ø10 rod + PVC insulating nuts.
Cold-storage ceilings are suspended from the building’s primary structure (trusses / HEB beams) on Ø10 threaded rods arranged in an approx. 1×1 m grid.
Critical installation aspects
- Ø10 rod is standard for cold/freezer rooms with chamber width <8 m.
- PVC nut + PVC washer ABSOLUTELY REQUIRED.
- 3-layer seal (PUR + sealant + PES).
- Rod spacing per structural design + loads (typically 1×1 m).
Documentation
GS insPIRe® CH Cold-storage Catalogue (Gór-Stal 2025), page 26 — Fixing of ceiling panels to the supporting structure. Scale 1:5.
Components in this junction
Panel (1)
- 01 GS insPIRe® CH / CH MAX cold-storage panel (insPIRe CH)
Accessory (2)
- 03 PVC insulating nut with steel insert
- 04 PVC mounting washer
Fastener (2)
- 05 Galvanised steel threaded rod Ø10
- 06 Galvanised steel M10 nut + washer
Sealant (3)
- 07 Polyurethane assembly foam
- 08 Permanently plastic sealing compound
- 09 PES sealing tape
Element (1)
- 02 Supporting structure