Base · GS MW

Floor mounting — vertical GS MW U panel layout

Bottom fixing of vertical GS MW U panels directly to concrete floor (without base beam). Identical construction as in S/CH (page 20): OB-42 channel, OB-05 flashing, mineral wool in the installation cavity.

Floor mounting — vertical GS MW U panel layout

Junction function

Vertical GS MW U floor = direct fixing to floor without base beam; construction identical to S/CH (page 18), but with U panel featuring concealed fixing.

Critical installation aspects

  • OB-42 channel raised 30 mm above floor level (waterproofing).
  • Expansion anchors every 60 cm in the central zone, 40 cm in the edge zone.
  • Mineral wool inside the channel — acoustics + EI 30.
  • System water resistance — without drip flashing only for internal halls or floors elevated above ground level.

Documentation

Technical Catalogue GS MW S/CH/U (Gór-Stal 2025), page 47 — Floor mounting, vertical U layout. Scale 1:5.

Components in this junction

Panel (1)
Insulation (1)
  • 04
    Rock mineral wool infill
Flashing (2)
Fastener (3)
  • 05
    Self-drilling fastener for sandwich panels
  • 06
    Self-drilling fastener for sheet metal or 4.0×8.0 rivet
  • 07
    Steel quick-mount expansion anchor